Can you please share the ideal behavior of RLAST in ACE5 two-part DVM transaction? Is there a value for RLAST to be fixed?

If possible, please provide additional details about the recognition of two responses.

 IHI0022H_amba_axi_protocol_spec.pdf

Parents
  • RLAST = 1 for both responses as these are two separate AR requests that make up the two part DVM.

    When a DVM is outstanding, the ARID used must not be used for other transaction types.  Therefore, the manager can recognise which responses are associated with a DVM.

Reply
  • RLAST = 1 for both responses as these are two separate AR requests that make up the two part DVM.

    When a DVM is outstanding, the ARID used must not be used for other transaction types.  Therefore, the manager can recognise which responses are associated with a DVM.